Timeline | ||
Year | Month | Event |
2005
| March | C & D site approved originally by Nova Scotia Environment (NSE). Expiry date for this approval was March 2015. Issued to M. R. Poole. |
October | Asbestos disposal facility approved originally by NSE. Expiry date for this approval was October 2015. | |
2007 | February | C & D site transferred ownership to Arlington Heights C & D. |
2015
| February | C & D site approval is renewed by NSE. |
Novem ber | Asbestos facility approval is renewed by NSE. Expiry date set for August 2017. | |
2017
|
March
| Application is made for an Environmental Assessment Approval for the asbestos disposal site. All application and supporting material is made available on NSE’s website. |
7th - Public notice was posted in the Chronicle Herald seeking comments from the public. | ||
8th - Public notice was posted in the Valley Register seeking comments from the public. | ||
April | 6th - Public consultation ended. | |
July | 24th - Environmental Assessment was approved by the Minister of Environment. | |
2018 | January | 29th - Asbestos Storage and/or Disposal Facility operational approval issued to Arlington Heights C & D Limited. Approval expires July 25, 2027. This is a separate approval from the Environmental Assessment Approval. Renewal of the approval issued in 2005 and again in 2015. |